Refit handover transfers technical control from the project team to the yacht only when the final installed configuration, as-built drawings, manuals, software and settings, equipment identities, test records, open defects, spares and maintenance data are reconciled. Reliable warranty-period management also records the exact commencement and expiry basis for each applicable warranty, keeps supplier contacts and claim procedures accessible, preserves service and defect evidence, tracks outstanding actions and ensures early-life failures are claimed, repaired, verified and documented before responsibility or evidence is lost.

Last verified: Aug. 10, 2026

Technical handover transfers engineering control rather than merely ending the refit project

A refit is not technically handed over simply because contractors demobilise or the yacht leaves the yard. The operating engineering team must receive enough verified information to understand, maintain and troubleshoot the final installed configuration. Wärtsilä Online brings current manuals, service bulletins, service history and warranty-claim information together as lifecycle operating information. The same principle applies to refit closeout: knowledge created during the project must become controlled yacht information rather than remain with the temporary project team.

The final equipment register should match what is physically installed

Reconcile modified machinery against the yacht's equipment register before handover. Record manufacturer, model, serial number, installed component identity and other configuration data needed for maintenance, spares and technical support. Refit substitutions and late changes can make a pre-project equipment list obsolete even when the work itself was successful. Future spare selection, service enquiries and warranty claims depend on engineers being able to identify the actual installed equipment rather than the component originally specified.

As-built drawings should replace construction-stage and red-line information

Final piping, electrical, control, structural and installation drawings should describe the yacht that was actually accepted. Construction drawings and field red-lines can be essential during the project, but they should not remain the only record of completed modifications. DNV's vessel-document environment treats current vessel documentation as operational material used in surveys and audits. Reconcile drawing revisions and clearly identify superseded material so engineers do not troubleshoot against an abandoned construction arrangement.

Current manuals, service bulletins and service history belong in the operating technical library

Wärtsilä Online provides access to up-to-date technical manuals, service bulletins and service history because machinery support continues after installation. Handover should verify that the yacht has the correct current technical information for the installed equipment and that project service reports are retained with the appropriate assets. Do not assume that manuals supplied before the refit still cover replacement machinery, upgraded controllers or service modifications introduced during the work.

Software versions, parameters and configuration backups are part of the final as-built condition

For automation, propulsion controls, power management, HVAC, stabilisation and other software-dependent systems, record the final accepted software or firmware version and relevant approved parameter state. Preserve identifiable configuration backups where the OEM system supports them. Temporary commissioning files or earlier backups should not be labelled as the final configuration. A future engineer restoring an unidentified pre-refit backup can unintentionally recreate obsolete logic, addresses or settings even though the hardware remains unchanged.

Acceptance and commissioning evidence should remain available after the witnesses leave

Retain the test procedures, signed results, instrument references, failed-test history, retest evidence and relevant factory, harbour and sea-trial records needed to demonstrate the accepted condition. Commissioning records establish what was proved and under which operating conditions. They can later provide the known-good reference when an early-life failure occurs. A handover package containing only final pass certificates can lose important evidence if earlier failed tests and corrective actions are removed from the engineering history.

Open defects, concessions and outstanding approval actions must remain visible at handover

DNV alteration-project status distinguishes completed documentation and closed approval comments from outstanding actions. A yacht's own handover should apply equivalent visibility to unresolved defects, temporary repairs, operating restrictions, warranty claims and outstanding survey or supplier actions. Clearly identify each remaining item, its owner, status, acceptance basis and next action. Handover should never convert an unresolved technical item into an invisible one merely because the refit contract reached its scheduled completion date.

Warranty commencement and expiry should be taken from the actual governing terms

Different equipment, work packages and suppliers can have different warranty commencement events and durations. Record the actual contractual basis for each important warranty, such as the applicable delivery, commissioning, acceptance or other defined date, together with the corresponding expiry or calculation method. Do not impose one universal yacht-wide warranty period or copy a manufacturer's general website statement when project-specific supply or service terms govern the installed item.

Warranty contacts and claim procedures should be usable by the operating engineering team

Wärtsilä Online allows users to register and follow warranty claims, illustrating the operational value of retaining an accessible claim route after handover. Record the relevant supplier, yard, OEM or service contact, claim reference process and documentation requirements for significant refit equipment. Portal access should transfer to the appropriate operating personnel where permitted. A warranty has limited practical value if the crew cannot identify who must be notified or what information must accompany a claim.

The warranty period should include active defect and service-history management

Early operating defects should be recorded promptly with equipment identity, operating context, alarms, photographs, measurements and service history while the evidence is available. Preserve the distinction between the technical defect and the commercial warranty claim, but link their references. The warranty-period register should show notification, supplier response, inspection, authorised repair, verification and commercial status so an item is not assumed complete simply because a supplier attended onboard or provided a replacement component.

Evidence should be preserved before warranty repair changes the failure condition

When an early-life defect appears, preserve relevant alarms, controller logs, condition data, photographs, fluid samples and failed components before cleaning, resetting or dismantling where this can be done safely. Record emergency work that had to precede supplier inspection and retain removed items where warranty or root-cause examination may be required. The handover record should give the operating engineers enough supplier and warranty information to make this decision before valuable failure evidence is destroyed.

Critical spares, special tools and support resources should be reconciled at handover

Confirm that agreed project spares, maintenance kits, consumables, special tools, software interfaces and diagnostic equipment have been physically received and identified. Wärtsilä Online links equipment data, spare ordering, service history and warranty claims because these functions depend on accurate lifecycle information. Refit closeout should similarly ensure that installed replacement equipment has the correct spare and support strategy rather than leaving the yacht with an obsolete inventory intended for the removed machinery.

Planned maintenance should be updated for the final installed configuration

New machinery, overhauled equipment, changed lubricants, revised software and modified systems can alter maintenance tasks, running-hour bases, service intervals and inspection requirements. Update the PMS from the applicable OEM, class, statutory and approved project information before normal operation resumes. Preserve completed refit maintenance and overhaul history as the new starting point. Do not reset accumulated machinery history merely to make the post-refit maintenance record appear tidy unless the equipment-specific procedure genuinely requires a new counter or baseline.

Crew familiarisation and escalation routes are part of engineering handover

Where refit work changes operating interfaces, control philosophy, maintenance access or fault response, the engineering team should receive appropriate familiarisation from the yard, OEM or specialist as required by the project. Record the technical support and escalation routes for systems that need remote or specialist assistance. Training does not replace manuals or approved procedures, but it helps the crew recognise normal behaviour, preserve evidence during early faults and contact the correct support organisation before improvising changes to unfamiliar equipment.

A practical refit-handover and warranty-period management sequence

Begin with the final accepted physical configuration and reconcile every modified asset against the equipment register, model, serial number and installed component identity. Replace construction-stage drawings and field red-lines with controlled as-built documentation and assemble the correct current manuals, service bulletins, service history, software versions, parameter records and configuration backups. Preserve commissioning, harbour and sea-trial evidence together with failed-test and retest history. Carry forward every unresolved defect, concession, survey comment and temporary condition with a named owner and visible status. For each significant warranty, record the actual governing agreement, commencement basis, expiry calculation, supplier contact and claim procedure rather than assuming one universal period. Transfer portal access and technical support routes where appropriate, reconcile critical spares and special tools and update PMS tasks for the final installed machinery. During the warranty period, record early-life defects promptly, preserve evidence before repair, link technical defects to commercial claims and verify every repair before closure. Complete the refit handover only when the operating engineering team can identify the yacht's final configuration, locate its authoritative technical records, understand every remaining action and exercise the applicable warranty and support arrangements without depending on undocumented knowledge retained by the departed project team.

Sources and verification