Somers Cove Marina modernization — official Maryland DNR photograph

News

Maryland Starts $30m Somers Cove Marina Upgrade for Yachts to 150ft

Sept. 27, 2026 Operations

Image: Maryland Department of Natural Resources

Maryland has begun an approximately $30m Somers Cove Marina modernization in Crisfield, covering floating piers, bulkheads, shore utilities and flood protection.

Work has begun on an approximately $30 million modernization at Somers Cove Marina in Crisfield, Maryland, where the 515-slip facility accommodates boats and yachts up to 150 feet. The state-owned harbour is an established Chesapeake Bay stop, and the project combines marine infrastructure with measures intended to address flooding nearby.

Maryland's Department of Natural Resources announced the programme on 23 September, reporting that works had begun earlier in the month. Completion is expected within 18–24 months, so this is a multi-season construction project, not a finished improvement available to visiting vessels today.

Eight piers and 2,000 feet of bulkhead

The rehabilitation includes replacing eight of the marina's 15 piers with floating systems, building approximately 2,000 feet of new bulkhead and replacing the boat ramp. Water, electricity and other upland utilities will also be addressed, together with improved access.

Those facilities are central to the experience of crews planning a berth stay. During construction, captains should check current slip allocation, shore supply and safe access directly with the marina.

Flood resilience beside the waterfront

Maryland also plans five tide gates within a new drainage system to reduce tidal flooding at Somers Cove and adjacent properties. Stormwater management, landscaping and environmental measures are included in the wider project.

The work illustrates how a marina's infrastructure connects with its surrounding town. Improved piers may benefit visiting boats, while drainage and access affect residents and businesses along the same waterfront.

Gateway to Chesapeake cruising

Somers Cove covers more than 30 acres and offers 515 slips for boats up to 150 feet, or approximately 45.7 metres. According to the state, it welcomed 5,288 boaters in 2025 and also supports island connections and local maritime services.

The stated maximum vessel length is significant for the broader yacht sector, but not every slip accommodates a vessel of that size. Beam, draft and current operating restrictions still require individual confirmation.

Funding and construction programme

The state identifies Waterway Improvement grants, general-obligation bonds and transportation funding as the principal sources for the approximately $30 million package. Baltimore-based Dvorak LLC is the general contractor.

The project is forecast to take 18–24 months, making progress updates and construction notices important for future itineraries. Yacht operators considering Crisfield should confirm arrangements before arriving, particularly while pier replacement is underway.

Continue reading

All news

Superyacht Guide

Explore the superyacht world

Continue into the wider Superyacht Guide.

Business opportunities · Superyacht Guide

Reach the superyacht industry audience

Companies serving the superyacht market can discuss clearly identified advertising, sponsorship and business-profile opportunities. Commercial activity remains separate from independent editorial coverage.